Online tool · Brazilian Termination Law

Construction delayed? Calculate your damages.

Once the 180-day grace period is exceeded, what the developer owes depends on when you signed: for contracts signed on or after 28 December 2018, the statutory benchmark is 1% of the amount paid per month of delay; for earlier contracts, the benchmark is the penalty clause of your own contract. Enter the date and see which regime applies to your case.

⚠ Not a substitute for a lawyerInitial, educational estimate. Neither a positive nor a negative result replaces a professional review of your contract and receipts.
180-day grace periodA grace period of up to 180 calendar days must be expressly agreed, clearly and prominently. Enter delay already measured after the valid grace period; the tool neither validates the clause nor automatically deducts 180 days.
Legal basis and cut-off dateArt. 43-A, §2, of Law 4,591/64 (Termination Law — Law 13,786/2018): 1% per month on the amounts actually paid, with monetary adjustment. It is the benchmark for contracts signed on or after 28 December 2018; for earlier ones, the penalty clause of the contract governs.
Your situation

Why the date matters: the 1%-per-month figure was created by Law 13,786/2018, in force since 28 December 2018. Contracts signed on or after that date follow it; earlier contracts follow the penalty clause of the contract itself, and for those the calculator shows no percentage at all.

Enter only complete months after the valid grace period in your contract ends. The tool does not deduct the grace period: 180 calendar days are not necessarily six months. Partial months require a daily pro-rata calculation.

The developer is late.
See what your contract determines.

We handle claims against developers in São Paulo and serve clients worldwide, in English. Send your simulation on WhatsApp to have the contract and the receipts reviewed — subject to an individual review.

How we calculate

The formula, the article and the review date.

The arithmetic. It only runs when the signature date you enter is on or after 28 December 2018. In that case: monthly damages = amount actually paid × 1%; estimated total = monthly damages × the number of months of delay you enter. In code: monthly = paid × 0.01 and total = monthly × months. Nothing else goes in: the calculator applies no monetary adjustment, computes no interest and adds no other losses. On the termination alternative it calculates nothing at all — it simply repeats the amount you entered as paid, followed by a plus sign. If the date is earlier than 28 December 2018, the tool multiplies nothing by 1%: it returns the referral to a reading of the contract's penalty clause, because there is no statutory percentage to apply.

The basis is art. 43-A of Law 4,591/1964, added by Law 13,786/2018 (the "Termination Law"). The main clause provides that delivery "within 180 (one hundred and eighty) calendar days of the date contractually set as the expected date for completion of the development, provided this is expressly agreed, clearly and prominently", gives the buyer no ground to terminate and triggers no penalty for the developer. § 2 is the source of the 1%: once that period is exceeded and there is no termination, "the compliant buyer shall be owed, upon delivery of the unit, compensation of 1% (one per cent) of the amount actually paid to the developer for each month of delay, pro rata die, adjusted for inflation according to the index set in the contract". § 1 covers the other route: a buyer who did not cause the delay may terminate the contract, with return of the entirety of the amounts paid and of the agreed penalty, within 60 calendar days, adjusted under § 8 of art. 67-A. And § 3 forbids stacking the two — the monthly compensation of § 2 addresses late performance, while the penalty of § 1 addresses total non-performance. That whole regime, however, only reaches contracts signed on or after 28 December 2018, for the reason the next item explains.

The cut-off date: 28 December 2018

Law 13,786/2018 was published in the Federal Official Gazette on 28 December 2018 and, under its art. 4, came into force on the date of publication. That is why the 1%-per-month figure in art. 43-A, §2, is the statutory benchmark for contracts signed on or after 28 December 2018. For earlier ones, the Superior Court of Justice (STJ), when ruling on the repetitive appeals about construction delay, held that Law 13,786/2018 does not apply to contracts signed before it came into force (REsp 1.498.484/DF, Second Section, judged on 22 May 2019), on the basis of art. 5, XXXVI, of the Constitution and art. 6, §2, of the Law of Introduction to the Rules of Brazilian Law (LINDB) — a position repeated by the panels (REsp 1.947.698/MS, Fourth Panel, judged on 8 March 2022). One precision, to avoid a common misreading: that non-retroactivity sits in the reasoning and the headnote of the leading judgment, and is not a standalone repetitive-appeal thesis.

In a contract signed before 28 December 2018, therefore, the benchmark for late-performance damages is the penalty clause of the contract itself: in Topic 970 (REsp 1.498.484/DF, Second Section, judged on 22 May 2019) the STJ held that the moratory penalty clause serves to compensate for late performance of the obligation and, as a rule, where set at an amount equivalent to the rental value, rules out its accumulation with lost profits. If the clause sets 0.5%, then it is 0.5%. And where an adhesion contract sets a penalty clause only for the buyer's default, Topic 971 (REsp 1.614.721/DF and 1.631.485/DF, Second Section, judged on 22 May 2019) requires that clause to be used in fixing the compensation for the seller's default, with heterogeneous obligations converted into money by judicial assessment. The Topic 970 judgment also records the judge's power and duty to review the penalty clause equitably (art. 413 of the Civil Code), even of their own motion. None of that is estimated by a formula: it depends on reading the contract.

A worked example

A contract signed after 28 December 2018 — the case in which art. 43-A, §2, applies. Assume R$ 300,000 actually paid and five full months of compensable delay already established after the applicable contractual deadline. The tool does not derive calendar dates or validate the grace clause. Monthly damages are R$ 300,000 × 1% = R$ 3,000, and the estimated total is R$ 15,000. Additional losses require proof and assessment of entitlement and permitted accumulation, without compensating the same loss twice. Article 43-A, § 3, prohibits adding the termination penalty to monthly delay compensation. Had the same contract been signed before 28 December 2018, that 1% line would not exist: its place is taken by the penalty clause of the contract.

Additional losses require proof and assessment of entitlement and permitted accumulation, without compensating the same loss twice. Article 43-A, § 3, prohibits adding the termination penalty to monthly delay compensation. The total is a simulation subject to its assumptions, not a guaranteed minimum award.

What the estimate leaves out

The statute counts the delay pro rata die; the calculator works in whole months — the number you type. That is a simplification adopted here, and the law does not fix it. Also excluded are inflation adjustment (which follows your contract's index, not a general one), interest, rent paid during the delay, the contractual penalty and any moral damages. The total is a simulation subject to its assumptions, not a guaranteed minimum award.

There is also what the tool does not check. It assumes your contract carries the express, clear and prominent grace clause the main clause requires — without it, the 180 days do not apply. It does not verify that you are current on your instalments, a condition of § 2, nor that the unit has been delivered, the moment when compensation falls due. And it assumes a condominium development (incorporação imobiliária): a plot bought in a land subdivision follows Law 6,766/1979, whose art. 32-A, also added by Law 13,786/2018, deals with termination for the buyer's default and sets no 1%-per-month figure.

Legal basis: Law 4,591/1964, art. 43-A, main clause and §§ 1 to 3, added by Law 13,786/2018 (in force since 28 December 2018) · Earlier contracts: STJ, REsp 1.498.484/DF, Second Section, judged on 22 May 2019 (Topics 970 and 971) · Sources: planalto.gov.br and stj.jus.br · Page last reviewed: 22 August 2026
Questions & answers

Construction delays in Brazil: know your rights.

Is the 180-day grace clause really valid?

A grace period of up to 180 calendar days must be expressly agreed, clearly and prominently. Enter delay already measured after the valid grace period; the tool neither validates the clause nor automatically deducts 180 days.

How are construction delay damages calculated?

It depends on when the contract was signed. For contracts signed on or after 28 December 2018, the benchmark is art. 43-A, §2, of Law 4,591/64, added by Law 13,786/2018: 1% of the amount actually paid to the developer per month of delay, counted after the applicable contractual deadline, with monetary adjustment. Example: someone who paid R$ 300,000 and faced an 8-month delay can claim about R$ 24,000. For contracts signed before 28 December 2018 that percentage does not apply automatically — the amount comes from the penalty clause of the contract.

My contract was signed before 28 December 2018. Does the 1% per month apply?

Not automatically. Art. 43-A of Law 4,591/64 was added by Law 13,786/2018, which came into force on 28 December 2018, and the Superior Court of Justice (STJ), when ruling on the repetitive appeals about construction delay, held that Law 13,786/2018 does not apply to contracts signed before it came into force (REsp 1.498.484/DF, Second Section, judged on 22 May 2019). In those contracts the benchmark for late-performance damages is the penalty clause of the contract itself — if it sets 0.5%, then it is 0.5%. Where the contract sets a penalty clause only for the buyer’s default, that clause is used to fix the compensation owed by the seller, and heterogeneous obligations are converted into money by judicial assessment (STJ Topics 970 and 971). That is why reading the contract is essential.

What if I no longer want the property?

Once the grace period is exceeded, art. 43-A, §1, of Law 4,591/64, added by Law 13,786/2018, provides that a buyer who did not cause the delay may terminate the contract, with return of the entirety of the amounts paid and of the agreed penalty, within 60 calendar days. That rule applies to contracts signed on or after 28 December 2018; for earlier contracts, the consequences of termination depend on what the contract provides and on a review of the case. Choosing between damages and termination depends on your goals and deserves professional analysis.

Which documents do I need?

The purchase agreement (with the delivery date and grace clause), proof of everything you paid (slips, transfers, financing), the occupancy permit or the developer’s notices about delivery, and messages/e-mails about the delay. With these, the exact calculation and strategy are ready quickly.

Is there a deadline to file a claim?

Yes — claims are subject to limitation periods that vary with the type of request (as a rule up to 10 years for contractual obligations, though some courts apply shorter periods). The sooner you act, the lower the risk of losing amounts. Consult a lawyer as soon as possible.

Does this calculator replace a lawyer’s analysis?

No — under no circumstances. The estimate is educational and based only on what you enter. The actual amount depends on the contract, payment receipts, monetary adjustment and additional provable losses (such as rent you had to pay). A lawyer must review your specific case.